Site Work Method Statement - Laying Boardroom Floor

HS.MS.05

This building task Method Statement for Laying a Boardroom Floor has been filled in to illustrate the sort of issues that may need consideration when completing a method statement for laying a wooden floor. The task in this case would not normally need a method statement, but if you are on a large site the Principle Contractor may need to see one.

You may find it useful to use this worked example method statement in conjunction with the blank method statement template in this folder and the guidance notes on how to write a method statement. This method statement has been professionally written for a specific task and a specific location and should be used as a guide only. Method statements must be site specific and each site will have its own particular issues that need consideration.

Writing a Method Statement can be an important part of managing risks around the building site. Using a systematic method of looking at your work activities by first completing a suitable Risk Assessment and then creating a safe system of work on the Method Statement form you will go a long way to ensuring the safety of your employees on site. If you are a sub-contractor you may be asked to provide your method statements before starting work. These forms, when properly filled in, will show your prospective clients that you are serious about managing health and safety on site.

Site Work Method Statement - Laying Boardroom Floor is part of Health and Safety Documents. Just £35.00 + VAT provides unlimited downloads from Health and Safety Documents for 1 year.

Simply-4-Business Ltd Registered in England and Wales No. 4868909 Unit 100, Parkway House, Sheen Lane, London SW14 8LS

Top